Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
Projectors, Ceiling mounted, Elementary and Middle Schools | 2,500,000 | | 220,000 | 2,280,000 | September 2008 | August 2010 / On Target |
Model Technology School Pilot | 775,000 | | 545,014 | 229,986 | September 2008 | May 2010 / On Target |
Video Distribution Upgrade | 225,000 | | | 225,000 | September 2008 | December 2009 / On Target |
Computer Replacement Cycle | 4,000,000 | | 813,724 | 3,186,276 | June 2008 | August 2010 / On Target |
Total Student Instruction - Technology Improvements | 7,500,000 | | 1,571,979 | 5,928,021 | | |